Assessment Year | 2011 |
---|---|
Principal Product | Thermoformed plastic food packaging |
NAICS | 326121: Unlaminated Plastics Profile Shape Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 152 |
Plant Area |
390,000
ft2
|
Annual Production | 20,300,000
lb
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $910,345 | 16,749,549 |
kWh
|
$0.054 |
Electricity Demand | $473,788 | 32,140 |
kW-mo/yr
|
$14.74 |
Natural Gas | $230,287 | 31,008 |
MMBtu
|
$7.43 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $183,219 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $16,753 | $200 |
$12,213
224,715
kWh
|
$4,540
-
kW-mo/yr
|
- | |
02 | 2.2511: Insulate bare equipment | $11,887 | $2,716 |
$8,674
159,599
kWh
|
$3,213
-
kW-mo/yr
|
- | |
03 | 2.4221: Install compressor air intakes in coolest locations | $11,502 | $10,000 |
$8,407
154,679
kWh
|
$3,095
-
kW-mo/yr
|
- | |
04 | 2.7314: Reduce ventilation air | $109,437 | $163,095 | - | - |
$109,437
-
MMBtu
|
|
05 | 2.2449: Recover heat from exhausted steam, hot air or hot water | $27,012 | $59,940 | - | - |
$27,012
-
MMBtu
|
|
06 | 2.2437: Recover waste heat from equipment | $6,628 | $5,000 | - | - |
$6,628
-
MMBtu
|
|
TOTAL RECOMMENDED | $183,219 | $240,951 |
$29,294
538,993
kWh
|
$10,848
-
kW-mo/yr
|
$143,077
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs