ITAC Assessment: UM0379
ITAC logo
ITAC Assessment: UM0379
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Board Insulation
NAICS 326140: Polystyrene Foam Product Manufacturing
SIC 3086: Plastics Foam Products
Sales Range $50
M
to 100
M
# of Employees 82
Plant Area 303,577
ft2
Annual Production 170,000,000
thousand feet
Production Hrs. Annual 8,760
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,144,273 16,985,048
kWh
Natural Gas $103,569 9,911
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $25,620 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,620

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,353 $14,633 $4,353
64,597
kWh
-
02 2.4221: Install compressor air intakes in coolest locations $1,706 $2,000 $1,706
25,313
kWh
-
03 2.6211: Conserve energy by efficient use of vending machines $229 $10 $229
3,400
kWh
-
04 2.2449: Recover heat from exhausted steam, hot air or hot water $9,060 $1,500 - $9,060
-
MMBtu
05 2.7491: Insulate glazing, walls, ceilings, and roofs $7,283 $9,861 - $7,283
-
MMBtu
06 2.2437: Recover waste heat from equipment $2,989 $1,350 - $2,989
-
MMBtu
TOTAL RECOMMENDED $25,620 $29,354 $6,288
93,310
kWh
$19,332
-
MMBtu
TOTAL IMPLEMENTED $25,620 $29,354 $6,288
93,310
kWh
$19,332
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs