ITAC Assessment: UM0377
ITAC logo
ITAC Assessment: UM0377
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2010
Principal Product Recycled Oil Products
NAICS 423930: Recyclable Material Merchant Wholesalers
SIC 5093: Scrap and Waste Materials
Sales Range $10
M
to 50
M
# of Employees 25
Plant Area 3,500
ft2
Annual Production 2,500
Tgal
Production Hrs. Annual 6,240
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,493 1,069,760
kWh
Electricity Demand $64,901 3,203
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $86,597 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
01 2.2622: Replace existing chiller with high efficiency model $4,826 $600,000 $2,496
60,010
kWh
$2,330
-
kW-mo/yr
- -
02 2.4224: Upgrade controls on compressors $4,594 $7,127 $4,594
110,448
kWh
- - -
03 2.4231: Reduce the pressure of compressed air to the minimum required $421 $200 $421
10,134
kWh
- - -
04 2.6211: Conserve energy by efficient use of vending machines $71 $10 $71
1,700
kWh
- - -
05 2.2128: Use steam condensate for hot water supply (non-potable) $47,701 $4,568 $28,797
2,424
kWh
- - $18,904
-
Tgal
06 2.2449: Recover heat from exhausted steam, hot air or hot water $11,037 $8,500 - - $11,037
-
MMBtu
-
07 2.1233: Analyze flue gas for proper air/fuel ratio $14,767 $700 - - $14,767
-
MMBtu
-
08 2.1243: Use heat from boiler blowdown to preheat boiler feed water $2,554 $11,607 - - $2,554
-
MMBtu
-
09 3.5112: Reprocess spent oils on site for re-use $626 $627 $68
1,652
kWh
- $558
-
MMBtu
-
TOTAL RECOMMENDED $86,597 $633,339 $36,447
186,368
kWh
$2,330
-
kW-mo/yr
$28,916
-
MMBtu
$18,904
-
Tgal
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Disposal Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs