| Assessment Year | 2010 |
|---|---|
| Principal Product | Military Armored Vehicles |
| NAICS | 336992: Military Armored Vehicle, Tank, and Tank Component Manufacturing |
| SIC | 3795: Tanks and Tank Components |
| Sales Range | greater than $500 M |
| # of Employees | 1,204 |
| Plant Area |
1,600,000
ft2
|
| Annual Production | 625
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $2,495,301 | 51,828,000 |
kWh
|
$0.048 |
| Natural Gas | $692,899 | 107,236 |
MMBtu
|
$6.46 |
| Coal | $1,641,600 | 266,996 |
MMBtu
|
$6.15 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $195,184 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $195,184 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Coal Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $126,231 | $236,764 |
$126,231
2,621,640
kWh
|
- | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $16,709 | $4,000 |
$16,709
347,020
kWh
|
- | - | |
| 03 | 2.7135: Install occupancy sensors | $7,646 | $4,232 |
$7,646
158,802
kWh
|
- | - | |
| 04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $27,796 | $140,490 | - |
$2,906
-
MMBtu
|
$24,890
-
MMBtu
|
|
| 05 | 2.2437: Recover waste heat from equipment | $16,802 | $5,500 | - |
$1,756
-
MMBtu
|
$15,046
-
MMBtu
|
|
| TOTAL RECOMMENDED | $195,184 | $390,986 |
$150,586
3,127,462
kWh
|
$4,662
-
MMBtu
|
$39,936
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $195,184 | $390,986 |
$150,586
3,127,462
kWh
|
$4,662
-
MMBtu
|
$39,936
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs