| Assessment Year | 2009 |
|---|---|
| Principal Product | Coal feeders and spouts |
| NAICS | 332510: Hardware Manufacturing |
| SIC | 3443: Fabricated Plate Work (Boiler Shops) |
| Sales Range | $1 M to 5M |
| # of Employees | 83 |
| Plant Area |
140,000
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 2,730
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $68,707 | 1,361,040 |
kWh
|
$0.050 |
| Electricity Demand | $68,368 | 3,991 |
kW-mo/yr
|
$17.13 |
| Natural Gas | $361,094 | 32,619 |
MMBtu
|
$11.07 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $172,435 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $172,435 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7494: Install storm windows and doors | $88,261 | $361,980 | - | - |
$88,261
-
MMBtu
|
|
| 02 | 2.7231: Use radiant heater for spot heating | $48,733 | $25,000 | - | - |
$48,733
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $17,053 | $42,818 |
$6,467
128,112
kWh
|
$10,586
-
kW-mo/yr
|
- | |
| 04 | 2.7491: Insulate glazing, walls, ceilings, and roofs | $5,524 | $2,591 | - | - |
$5,524
-
MMBtu
|
|
| 05 | 2.2136: Install / repair insulation on steam lines | $1,523 | $1,359 | - | - |
$1,523
-
MMBtu
|
|
| 06 | 2.7135: Install occupancy sensors | $1,466 | $4,692 |
$1,466
34,510
kWh
|
- | - | |
| 07 | 2.4226: Use / purchase optimum sized compressor | $9,875 | $7,500 |
$3,811
81,847
kWh
|
$6,064
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $172,435 | $445,940 |
$11,744
244,469
kWh
|
$16,650
-
kW-mo/yr
|
$144,041
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $172,435 | $445,940 |
$11,744
244,469
kWh
|
$16,650
-
kW-mo/yr
|
$144,041
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs