| Assessment Year | 1984 |
|---|---|
| Principal Product | MARGARINE, SHORTENING |
| NAICS |
n/a
|
| SIC | 2079: Shortening, Table Oils, Margarine, and Other Edible Fats and Oils, Not Elsewhere Classified |
| Sales Range | $10 M to 50M |
| # of Employees | 168 |
| Plant Area |
n/a
|
| Annual Production | 90,000,000
lb
|
| Production Hrs. Annual | 2,600
hrs
|
| Location (State) | Ohio |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $286,024 | 5,002,638 |
kWh
|
$0.057 |
| Natural Gas | $279,115 | 48,317 |
MMBtu
|
$5.78 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $78,274 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $33,545 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4133: Use most efficient type of electric motors | $947 | $1,280 |
$947
14,947
kWh
|
- | |
| 02 | 2.2522: Isolate hot or cold equipment | $2,075 | $1,240 |
$858
30,481
kWh
|
$1,217
-
MMBtu
|
|
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,348 | $708 |
$2,705
27,550
kWh
|
$(-357.0)
-
MMBtu
|
|
| 04 | 2.2511: Insulate bare equipment | $21,331 | $10,185 |
$2,870
50,117
kWh
|
$18,461
-
MMBtu
|
|
| 05 | 2.2121: Increase amount of condensate returned | $3,213 | $3,000 | - |
$3,213
-
MMBtu
|
|
| 06 | 2.1224: Replace boiler | $40,533 | $25,000 | - |
$40,533
-
MMBtu
|
|
| 07 | 3.4115: Recover and reuse cooling water | $1,755 | - |
$1,755
30,188
kWh
|
- | |
| 08 | 2.2437: Recover waste heat from equipment | $983 | $1,500 | - |
$983
-
MMBtu
|
|
| 09 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $5,089 | $3,000 |
$5,089
-
kWh
|
- | |
| TOTAL RECOMMENDED | $78,274 | $45,913 |
$14,224
153,283
kWh
|
$64,050
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $33,545 | $16,413 |
$14,224
153,283
kWh
|
$19,321
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs