ITAC Assessment: UM0354
ITAC logo
ITAC Assessment: UM0354
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product RV Toilets
NAICS 326191: Plastics Plumbing Fixture Manufacturing
SIC 3088: Plastics Plumbing Fixtures
Sales Range $10
M
to 50
M
# of Employees 142
Plant Area 240,000
ft2
Annual Production 2,578,300
pieces
Production Hrs. Annual 2,210
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $117,553 2,567,810
kWh
Electricity Demand $119,361 7,377
kW-mo/yr
Natural Gas $106,417 10,146
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $75,650 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $47,586

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $24,576 $69,141 $10,280
190,640
kWh
$14,296
-
kW-mo/yr
-
02 2.7243: Improve air circulation with destratification fans / other methods $17,778 $8,750 - - $17,778
-
MMBtu
03 2.7447: Install vinyl strip / high speed / air curtain doors $13,567 $9,570 $13,567
1,307
kWh
- -
04 2.7221: Lower temperature during the winter season and vice-versa $12,144 $4,200 - - $12,144
-
MMBtu
05 2.6218: Turn off equipment when not in use $3,488 - $3,488
75,712
kWh
- -
06 2.2437: Recover waste heat from equipment $3,114 $500 - - $3,114
-
MMBtu
07 2.4231: Reduce the pressure of compressed air to the minimum required $983 $200 $420
9,148
kWh
$563
-
kW-mo/yr
-
TOTAL RECOMMENDED $75,650 $92,361 $27,755
276,807
kWh
$14,859
-
kW-mo/yr
$33,036
-
MMBtu
TOTAL IMPLEMENTED $47,586 $23,220 $13,987
10,455
kWh
$563
-
kW-mo/yr
$33,036
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs