| Assessment Year | 2020 |
|---|---|
| Principal Product | Ice cream and novelties |
| NAICS | 311520: Ice Cream and Frozen Dessert Manufacturing |
| SIC | 2024: Ice Cream and Frozen Desserts |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
141,912
ft2
|
| Annual Production | 10,500,000
pieces
|
| Production Hrs. Annual | 8,720
hrs
|
| Location (State) | Utah |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $1,056,233 | 32,117,120 |
kWh
|
$0.033 | |
| Electricity Demand | $833,677 | 61,345 |
kW-mo/yr
|
$13.59 | |
| Electricity Fees | $150,865 | - |
|
- | |
| Natural Gas | $270,305 | 74,100 |
MMBtu
|
$3.65 | |
| Waste Disposal Costs | |||||
| Water Usage | $56,754 | 37,806 |
Tgal
|
$1.50 | |
| Water Disposal | $150,846 | 37,806 |
Tgal
|
$3.99 | |
| Other Liquid (haz) | $825,305 | 87,413,496 |
gal
|
$0.009 | |
| TOTAL YEARLY COSTS | $3,343,985 | ||||
| RECOMMENDED SAVINGS* | $84,025 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | $76,195 | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.4131: Minimize contamination of water before treatment | $43,260 | $86,000 | - | - | - | - | $43,260 | |
| 02 | 2.7496: Install partitions to reduce size of conditioned space | $22,840 | $53,000 |
$4,840
146,640
kWh
|
- | - | $18,000 | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $8,315 | $7,880 |
$8,585
260,170
kWh
|
- | - | $(-270.0) | - | |
| 04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $5,370 | $5,370 |
$3,150
95,420
kWh
|
$2,220
-
kW-mo/yr
|
- | - | - | |
| 05 | 2.2522: Isolate hot or cold equipment | $2,460 | $9,000 |
$(-1,670.0)
(-50,460)
kWh
|
$(-940.0)
-
kW-mo/yr
|
$5,070
-
MMBtu
|
- | - | |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,780 | $6,880 |
$1,130
34,430
kWh
|
$650
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $84,025 | $168,130 |
$16,035
486,200
kWh
|
$1,930
-
kW-mo/yr
|
$5,070
-
MMBtu
|
$17,730 | $43,260 | ||
| TOTAL IMPLEMENTED | $76,195 | $153,760 |
$14,555
441,240
kWh
|
$650
-
kW-mo/yr
|
- | $17,730 | $43,260 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs