| Assessment Year | 2009 |
|---|---|
| Principal Product | Capital Equipment for Heat Exchanger Industry |
| NAICS | 333517: Machine Tool Manufacturing |
| SIC | 3542: Machine Tools, Metal Forming Types |
| Sales Range | $50 M to 100M |
| # of Employees | 350 |
| Plant Area |
250,000
ft2
|
| Annual Production | 300
pieces
|
| Production Hrs. Annual | 5,928
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $482,996 | 10,568,335 |
kWh
|
$0.046 |
| Electricity Demand | $318,408 | 25,720 |
kW-mo/yr
|
$12.38 |
| Natural Gas | $51,281 | 5,447 |
MMBtu
|
$9.41 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $58,558 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $52,412 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.6218: Turn off equipment when not in use | $37,050 | - |
$22,442
491,081
kWh
|
$14,608
-
kW-mo/yr
|
- | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,706 | $19,921 |
$7,393
161,767
kWh
|
$6,313
-
kW-mo/yr
|
- | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,516 | $100 |
$1,347
29,465
kWh
|
$1,169
-
kW-mo/yr
|
- | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $2,124 | $2,800 | - | - |
$2,124
-
MMBtu
|
|
| 05 | 2.7221: Lower temperature during the winter season and vice-versa | $1,656 | $500 | - | - |
$1,656
-
MMBtu
|
|
| 06 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,506 | $1,660 | - | - |
$1,506
-
MMBtu
|
|
| TOTAL RECOMMENDED | $58,558 | $24,981 |
$31,182
682,313
kWh
|
$22,090
-
kW-mo/yr
|
$5,286
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $52,412 | $20,421 |
$29,835
652,848
kWh
|
$20,921
-
kW-mo/yr
|
$1,656
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs