Assessment Year | 2008 |
---|---|
Principal Product | Rotational and Blow Molded Plastic Products |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 55 |
Plant Area |
75,000
ft2
|
Annual Production | 500,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $52,163 | 2,028,540 |
kWh
|
$0.026 |
Electricity Demand | $71,433 | 4,992 |
kW-mo/yr
|
$14.31 |
Natural Gas | $219,930 | 24,145 |
MMBtu
|
$9.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $48,261 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2414: Use waste heat from hot flue gases to preheat | $9,638 | $8,898 | - | - |
$9,638
-
MMBtu
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,545 | $6,240 |
$2,161
84,076
kWh
|
$2,384
-
kW-mo/yr
|
- | |
03 | 2.2514: Cover open tanks | $2,233 | $1,046 |
$932
29,241
kWh
|
$1,301
-
kW-mo/yr
|
- | |
04 | 2.7135: Install occupancy sensors | $1,503 | $500 |
$1,503
24,637
kWh
|
- | - | |
05 | 2.4221: Install compressor air intakes in coolest locations | $452 | $422 |
$145
5,658
kWh
|
$307
-
kW-mo/yr
|
- | |
06 | 2.1123: Install automatic stack damper | $29,890 | $8,100 | - | - |
$29,890
-
MMBtu
|
|
TOTAL RECOMMENDED | $48,261 | $25,206 |
$4,741
143,612
kWh
|
$3,992
-
kW-mo/yr
|
$39,528
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs