ITAC Assessment: UM0347
ITAC logo
ITAC Assessment: UM0347
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Rotational and Blow Molded Plastic Products
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 55
Plant Area 75,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,163 2,028,540
kWh
Electricity Demand $71,433 4,992
kW-mo/yr
Natural Gas $219,930 24,145
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $48,261 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2414: Use waste heat from hot flue gases to preheat $9,638 $8,898 - - $9,638
-
MMBtu
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,545 $6,240 $2,161
84,076
kWh
$2,384
-
kW-mo/yr
-
03 2.2514: Cover open tanks $2,233 $1,046 $932
29,241
kWh
$1,301
-
kW-mo/yr
-
04 2.7135: Install occupancy sensors $1,503 $500 $1,503
24,637
kWh
- -
05 2.4221: Install compressor air intakes in coolest locations $452 $422 $145
5,658
kWh
$307
-
kW-mo/yr
-
06 2.1123: Install automatic stack damper $29,890 $8,100 - - $29,890
-
MMBtu
TOTAL RECOMMENDED $48,261 $25,206 $4,741
143,612
kWh
$3,992
-
kW-mo/yr
$39,528
-
MMBtu
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs