| Assessment Year | 2014 |
|---|---|
| Principal Product | Railroad Ties |
| NAICS | 321114: Wood Preservation |
| SIC | 2491: Wood Preserving |
| Sales Range | $50 M to 100M |
| # of Employees | 80 |
| Plant Area |
200,000
ft2
|
| Annual Production | 1,200,000
pieces
|
| Production Hrs. Annual | 2,550
hrs
|
| Location (State) | Alabama |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $299,499 | 4,284,595 |
kWh
|
$0.070 |
| Electricity Fees | $11,909 | - |
|
- |
| Wood | $148,000 | 77,969 |
MMBtu
|
$1.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $190,836 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,170 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Wood Savings |
|---|---|---|---|---|---|---|
| 01 | 4.132: Purchase new equipment to reduce material use / cost | $125,709 | $180,000 | - |
$125,709
-
MMBtu
|
|
| 02 | 2.2136: Install / repair insulation on steam lines | $24,552 | $12,050 | - |
$24,552
-
MMBtu
|
|
| 03 | 2.2414: Use waste heat from hot flue gases to preheat | $13,032 | $35,000 | - |
$13,032
-
MMBtu
|
|
| 04 | 2.1113: Reduce combustion air flow to optimum | $11,022 | $7,500 | - |
$11,022
-
MMBtu
|
|
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $10,193 | $6,764 |
$10,193
130,995
kWh
|
- | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,565 | $6,495 |
$3,565
48,254
kWh
|
- | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,158 | $7,334 |
$2,158
29,205
kWh
|
- | |
| 08 | 2.7134: Use photocell controls | $605 | $1,725 |
$605
8,193
kWh
|
- | |
| TOTAL RECOMMENDED | $190,836 | $256,868 |
$16,521
216,647
kWh
|
$174,315
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $4,170 | $8,220 |
$4,170
56,447
kWh
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Wood Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs