| Assessment Year | 2008 |
|---|---|
| Principal Product | instrument panels, headliners, center console |
| NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
228,000
ft2
|
| Annual Production | 198,000
pieces
|
| Production Hrs. Annual | 4,200
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,069,807 | 25,800,000 |
kWh
|
$0.041 |
| Natural Gas | $412,272 | 48,054 |
MMBtu
|
$8.58 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $22,309 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $11,291 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $10,365 | $7,499 |
$10,365
94,610
kWh
|
- | |
| 02 | 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available | $8,397 | $1,650 |
$8,397
100,212
kWh
|
- | |
| 03 | 2.3132: Recharge batteries on during off-peak demand periods | $1,558 | - | - |
$1,558
-
kW-mo/yr
|
|
| 04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,336 | $460 |
$1,336
11,483
kWh
|
- | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $653 | $544 |
$653
6,313
kWh
|
- | |
| TOTAL RECOMMENDED | $22,309 | $10,153 |
$20,751
212,618
kWh
|
$1,558
-
kW-mo/yr
|
||
| TOTAL IMPLEMENTED | $11,291 | $2,110 |
$9,733
111,695
kWh
|
$1,558
-
kW-mo/yr
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs