ITAC Assessment: UM0336
ITAC logo
ITAC Assessment: UM0336
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2008
Principal Product Brass Fluid Connectors
NAICS 331529: Other Nonferrous Metal Foundries (except Die-Casting)
SIC 3366: Copper Foundries
Sales Range $10
M
to 50
M
# of Employees 450
Plant Area 190,000
ft2
Annual Production 20,800,000
lb
Production Hrs. Annual 6,240
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $511,447 10,212,168
kWh
Electricity Demand $200,966 20,170
kW-mo/yr
Electricity Fees $24,547 -
Natural Gas $71,283 8,439
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $89,895 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $58,675

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $31,330 $1,650 $22,801
445,308
kWh
$8,529
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $17,116 $200 $12,381
247,299
kWh
$4,735
-
kW-mo/yr
-
03 2.7492: Use proper thickness of insulation on building envelope $13,866 $29,119 - - $13,866
-
MMBtu
04 2.7314: Reduce ventilation air $8,256 $2,001 - - $8,256
-
MMBtu
05 2.7447: Install vinyl strip / high speed / air curtain doors $6,239 $10,900 - - $6,239
-
MMBtu
06 2.7135: Install occupancy sensors $6,297 $1,600 $6,297
125,736
kWh
- -
07 2.7111: Reduce illumination to minimum necessary levels $3,932 $1,000 $2,844
56,784
kWh
$1,088
-
kW-mo/yr
-
08 2.6218: Turn off equipment when not in use $2,766 $260 $2,766
55,224
kWh
- -
09 2.7447: Install vinyl strip / high speed / air curtain doors $93 $93 - - $93
-
MMBtu
TOTAL RECOMMENDED $89,895 $46,823 $47,089
930,351
kWh
$14,352
-
kW-mo/yr
$28,454
-
MMBtu
TOTAL IMPLEMENTED $58,675 $4,450 $44,323
875,127
kWh
$14,352
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs