Assessment Year | 2008 |
---|---|
Principal Product | Automotive Mirror Assemblies |
NAICS | 336390: Other Motor Vehicle Parts Manufacturing |
SIC | 3714: Motor Vehicle Parts and Accessories |
Sales Range | $100 M to 500M |
# of Employees | 704 |
Plant Area |
228,000
ft2
|
Annual Production | 7,000,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $974,701 | 22,606,815 |
kWh
|
$0.043 |
Electricity Demand | $716,322 | 45,273 |
kW-mo/yr
|
$15.82 |
Electricity Fees | $9,086 | - |
|
- |
Natural Gas | $409,550 | 41,127 |
MMBtu
|
$9.96 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $248,747 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,524 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2437: Recover waste heat from equipment | $89,698 | $182,750 |
$(-10,290.0)
(-238,615)
kWh
|
$(-11,325.0)
-
kW-mo/yr
|
$111,313
-
MMBtu
|
|
02 | 2.2437: Recover waste heat from equipment | $74,186 | $72,325 |
$(-643.0)
(-14,914)
kWh
|
$(-708.0)
-
kW-mo/yr
|
$75,537
-
MMBtu
|
|
03 | 2.7314: Reduce ventilation air | $36,521 | $12,950 | - | - |
$36,521
-
MMBtu
|
|
04 | 2.2437: Recover waste heat from equipment | $31,917 | $18,591 | - | - |
$31,917
-
MMBtu
|
|
05 | 2.7221: Lower temperature during the winter season and vice-versa | $7,221 | $500 | - | - |
$7,221
-
MMBtu
|
|
06 | 2.7111: Reduce illumination to minimum necessary levels | $5,331 | $15,000 |
$3,544
82,188
kWh
|
$1,787
-
kW-mo/yr
|
- | |
07 | 2.7442: Keep doors and windows shut when not on use | $1,972 | $50 | - | - |
$1,972
-
MMBtu
|
|
08 | 2.2414: Use waste heat from hot flue gases to preheat | $1,901 | $1,621 |
$(-140.0)
(-3,257)
kWh
|
$(-71.0)
-
kW-mo/yr
|
$2,112
-
MMBtu
|
|
TOTAL RECOMMENDED | $248,747 | $303,787 |
$(-7,529.0)
(-174,598)
kWh
|
$(-10,317.0)
-
kW-mo/yr
|
$266,593
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,524 | $15,550 |
$3,544
82,188
kWh
|
$1,787
-
kW-mo/yr
|
$9,193
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs