ITAC Assessment: GT0742
ITAC logo
ITAC Assessment: GT0742
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Bottle Capping Machines
NAICS
n/a
SIC 3565: Packaging Machinery
Sales Range $10
M
to 50
M
# of Employees 87
Plant Area 69,460
ft2
Annual Production 44
units
Production Hrs. Annual 2,000
hrs
Location (State) Georgia

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $40,797 677,440
kWh
Electricity Demand $18,544 306
kW-mo/yr
Electricity Fees $2,472 -
Natural Gas $12,200 1,422
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $21,924 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $21,924

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings
01 2.7221: Lower temperature during the winter season and vice-versa $15,773 $1,400 $12,000
55,685
kWh
$3,773
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $4,487 $15,062 $2,782
28,722
kWh
$1,705
-
kW-mo/yr
-
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $710 $400 $485
4,396
kWh
$225
-
kW-mo/yr
-
04 2.4111: Utilize energy-efficient belts and other improved mechanisms $248 $475 $248
2,345
kWh
- -
05 3.5212: Regrind, reuse, or sell scrap plastic parts $706 - - - $706
-
lb
TOTAL RECOMMENDED $21,924 $17,337 $15,515
91,148
kWh
$5,703
-
kW-mo/yr
$706
-
lb
TOTAL IMPLEMENTED $21,924 $17,337 $15,515
91,148
kWh
$5,703
-
kW-mo/yr
$706
-
lb
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs