ITAC Assessment: UL0154
ITAC logo
ITAC Assessment: UL0154
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1996
Principal Product Steel Tubing, Tail Pipes
NAICS
n/a
SIC 3317: Steel Pipe and Tubes
Sales Range $10
M
to 50
M
# of Employees 250
Plant Area 80,000
ft2
Annual Production 0
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Kentucky

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $84,632 3,095,838
kWh
Electricity Demand $86,148 9,342
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,236 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $295 $1,548 $187
6,741
kWh
$108
-
kW-mo/yr
- -
02 2.4133: Use most efficient type of electric motors $160 $3,080 $97
3,517
kWh
$63
-
kW-mo/yr
- -
03 2.4231: Reduce the pressure of compressed air to the minimum required $202 $20 $88
2,345
kWh
$114
-
kW-mo/yr
- -
04 2.4221: Install compressor air intakes in coolest locations $289 $35 $126
4,689
kWh
$163
-
kW-mo/yr
- -
05 3.7214: Reduce or eliminate waste $7,500 $900 - - $7,500
-
gal
-
06 3.1191: Change procedures / equipment / operating conditions $3,040 $500 - - - $3,040
07 3.1162: Use less wasteful packaging $26,750 $36,000 - - - $26,750
TOTAL RECOMMENDED $38,236 $42,083 $498
17,292
kWh
$448
-
kW-mo/yr
$7,500
-
gal
$29,790
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (haz) Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs