Assessment Year | 1996 |
---|---|
Principal Product | Steel Tubing, Tail Pipes |
NAICS |
n/a
|
SIC | 3317: Steel Pipe and Tubes |
Sales Range | $10 M to 50M |
# of Employees | 250 |
Plant Area |
80,000
ft2
|
Annual Production | 0
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Kentucky |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $84,632 | 3,095,838 |
kWh
|
$0.027 |
Electricity Demand | $86,148 | 9,342 |
kW-mo/yr
|
$9.22 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $38,236 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $295 | $1,548 |
$187
6,741
kWh
|
$108
-
kW-mo/yr
|
- | - | |
02 | 2.4133: Use most efficient type of electric motors | $160 | $3,080 |
$97
3,517
kWh
|
$63
-
kW-mo/yr
|
- | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $202 | $20 |
$88
2,345
kWh
|
$114
-
kW-mo/yr
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $289 | $35 |
$126
4,689
kWh
|
$163
-
kW-mo/yr
|
- | - | |
05 | 3.7214: Reduce or eliminate waste | $7,500 | $900 | - | - |
$7,500
-
gal
|
- | |
06 | 3.1191: Change procedures / equipment / operating conditions | $3,040 | $500 | - | - | - | $3,040 | |
07 | 3.1162: Use less wasteful packaging | $26,750 | $36,000 | - | - | - | $26,750 | |
TOTAL RECOMMENDED | $38,236 | $42,083 |
$498
17,292
kWh
|
$448
-
kW-mo/yr
|
$7,500
-
gal
|
$29,790 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs