ITAC Assessment: UM0326
ITAC logo
ITAC Assessment: UM0326
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Metal Casting
NAICS 331512: Steel Investment Foundries
SIC 3324: Steel Investment Foundries
Sales Range $5
M
to 10
M
# of Employees 115
Plant Area 44,000
ft2
Annual Production 950,000
units
Production Hrs. Annual 6,240
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $123,588 2,558,080
kWh
Electricity Demand $73,890 7,898
kW-mo/yr
Electricity Fees $5,092 -
Natural Gas $128,222 13,816
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $52,075 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $25,293

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1233: Analyze flue gas for proper air/fuel ratio $26,782 $1,000 - - $26,782
-
MMBtu
02 2.1135: Repair furnaces and oven doors so that they seal efficiently $8,825 $13,130 - - $8,825
-
MMBtu
03 2.2514: Cover open tanks $4,631 $220 - - $4,631
-
MMBtu
04 2.2437: Recover waste heat from equipment $3,591 $500 - - $3,591
-
MMBtu
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,234 $675 $2,356
48,768
kWh
$878
-
kW-mo/yr
-
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,191 $1,860 $1,571
32,523
kWh
$620
-
kW-mo/yr
-
07 2.2414: Use waste heat from hot flue gases to preheat $1,476 $2,200 - - $1,476
-
MMBtu
08 2.4221: Install compressor air intakes in coolest locations $1,092 $204 $795
16,461
kWh
$297
-
kW-mo/yr
-
09 2.7135: Install occupancy sensors $253 $600 $253
5,242
kWh
- -
TOTAL RECOMMENDED $52,075 $20,389 $4,975
102,994
kWh
$1,795
-
kW-mo/yr
$45,305
-
MMBtu
TOTAL IMPLEMENTED $25,293 $19,389 $4,975
102,994
kWh
$1,795
-
kW-mo/yr
$18,523
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs