ITAC Assessment: UM0320
ITAC logo
ITAC Assessment: UM0320
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2007
Principal Product Suspension Components
NAICS 336330: Motor Vehicle Steering and Suspension Components (except Spring) Manufacturing
SIC 3714: Motor Vehicle Parts and Accessories
Sales Range $50
M
to 100
M
# of Employees 166
Plant Area 101,951
ft2
Annual Production 4,000,000
pieces
Production Hrs. Annual 5,760
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $330,608 11,333,827
kWh
Electricity Demand $381,288 24,631
kW-mo/yr
Electricity Fees $33,215 -
Natural Gas $147,879 15,271
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $123,254 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $89,688

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7314: Reduce ventilation air $20,841 $4,960 - - - $20,841
-
MMBtu
02 2.4235: Remove or close off unneeded compressed air lines $19,072 - $19,072
653,153
kWh
- - -
03 2.3131: Reschedule plant operations or reduce load to avoid peaks $12,725 $3,000 - $12,725
-
kW-mo/yr
- -
04 2.7244: Revise smoke cleanup from operations $11,829 $1,846 - - - $11,829
-
MMBtu
05 2.4235: Remove or close off unneeded compressed air lines $10,797 - $5,131
175,714
kWh
$5,666
-
kW-mo/yr
- -
06 2.3212: Optimize plant power factor $10,572 $19,721 - - $10,572 -
07 2.2437: Recover waste heat from equipment $7,938 $500 - - - $7,938
-
MMBtu
08 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $8,982 $825 $4,264
146,037
kWh
$4,718
-
kW-mo/yr
- -
09 2.4231: Reduce the pressure of compressed air to the minimum required $6,603 $20 $3,136
107,381
kWh
$3,467
-
kW-mo/yr
- -
10 2.4224: Upgrade controls on compressors $4,703 $1 $4,703
161,071
kWh
- - -
11 2.7122: Disconnect ballasts $3,782 - $3,782
129,504
kWh
- - -
12 2.7142: Utilize higher efficiency lamps and/or ballasts $4,510 $80 $2,142
73,354
kWh
$2,368
-
kW-mo/yr
- -
13 2.7224: Reduce space conditioning during non-working hours $900 $100 - - - $900
-
MMBtu
TOTAL RECOMMENDED $123,254 $31,053 $42,230
1,446,214
kWh
$28,944
-
kW-mo/yr
$10,572 $41,508
-
MMBtu
TOTAL IMPLEMENTED $89,688 $23,093 $42,230
1,446,214
kWh
$16,219
-
kW-mo/yr
$10,572 $20,667
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs