ITAC Assessment: UM0307
ITAC logo
ITAC Assessment: UM0307
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Ductile Iron Castings
NAICS 331511: Iron Foundries
SIC 3321: Gray and Ductile Iron Foundries
Sales Range $10
M
to 50
M
# of Employees 188
Plant Area 106,813
ft2
Annual Production 92,000,000
lb
Production Hrs. Annual 7,200
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $3,422,796 68,783,814
kWh
Electricity Demand $889,600 162,567
kW-mo/yr
Natural Gas $750,805 83,740
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $713,182 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $479,472

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.1135: Repair furnaces and oven doors so that they seal efficiently $302,929 $70,000 $302,929
8,205,000
kWh
- -
02 2.6212: Turn off equipment during breaks, reduce operating time $219,438 - $219,438
5,943,600
kWh
- -
03 2.6242: Minimize operation of equipment maintained in standby condition $63,131 - - - $63,131
-
MMBtu
04 2.1133: Adjust burners for efficient operation $55,043 $2,400 - - $55,043
-
MMBtu
05 2.1135: Repair furnaces and oven doors so that they seal efficiently $19,061 $5,066 - - $19,061
-
MMBtu
06 2.7447: Install vinyl strip / high speed / air curtain doors $14,621 $1,500 - - $14,621
-
MMBtu
07 2.2414: Use waste heat from hot flue gases to preheat $10,914 $5,000 - - $10,914
-
MMBtu
08 2.4239: Eliminate or reduce compressed air usage $10,428 $2,000 $8,364
226,536
kWh
$2,064
-
kW-mo/yr
-
09 2.7142: Utilize higher efficiency lamps and/or ballasts $6,814 $10,054 $5,249
142,182
kWh
$1,565
-
kW-mo/yr
-
10 2.2511: Insulate bare equipment $3,606 $1,191 - - $3,606
-
MMBtu
11 2.2437: Recover waste heat from equipment $3,358 $2,100 - - $3,358
-
MMBtu
12 2.2511: Insulate bare equipment $3,085 - $2,474
67,000
kWh
$611
-
kW-mo/yr
-
13 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $754 $75 $605
16,376
kWh
$149
-
kW-mo/yr
-
TOTAL RECOMMENDED $713,182 $99,386 $539,059
14,600,694
kWh
$4,389
-
kW-mo/yr
$169,734
-
MMBtu
TOTAL IMPLEMENTED $479,472 $92,286 $319,621
8,657,094
kWh
$4,389
-
kW-mo/yr
$155,462
-
MMBtu
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs