| Assessment Year | 2006 |
|---|---|
| Principal Product | Aerospace blades/vanes |
| NAICS | 333611: Turbine and Turbine Generator Set Units Manufacturing |
| SIC | 3511: Steam, Gas, and Hydraulic Turbines, and Turbine Generator Set Units |
| Sales Range | $10 M to 50M |
| # of Employees | 230 |
| Plant Area |
118,000
ft2
|
| Annual Production | 240,000
pieces
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Florida |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $792,307 | 10,035,284 |
kWh
|
$0.079 |
| Electricity Demand | $215,381 | 29,149 |
kW-mo/yr
|
$7.39 |
| Natural Gas | $596,546 | 41,239 |
MMBtu
|
$14.47 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $79,355 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $64,285 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2511: Insulate bare equipment | $1,545 | $2,803 |
$1,545
19,551
kWh
|
- | - | - | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $24,561 | $2,190 |
$24,561
310,903
kWh
|
- | - | - | |
| 03 | 2.6218: Turn off equipment when not in use | $7,957 | - |
$7,957
138,387
kWh
|
- | - | - | |
| 04 | 2.7229: Air condition only space necessary | $2,639 | $3,360 |
$2,639
45,895
kWh
|
- | - | - | |
| 05 | 2.7141: Lower light fixtures in high ceiling areas | $4,265 | $578 |
$3,626
63,072
kWh
|
$639
-
kW-mo/yr
|
- | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,577 | $370 |
$1,098
7,842
kWh
|
- | $352 | $127 | |
| 07 | 2.4131: Size electric motors for peak operating efficiency | $21,479 | - |
$17,222
299,520
kWh
|
$4,257
-
kW-mo/yr
|
- | - | |
| 08 | 2.7124: Make a practice of turning off lights when not needed | $2,017 | - |
$2,017
35,076
kWh
|
- | - | - | |
| 09 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,106 | $6,458 |
$11,088
192,842
kWh
|
$2,018
-
kW-mo/yr
|
- | - | |
| 10 | 2.7135: Install occupancy sensors | $209 | $140 |
$209
3,635
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $79,355 | $15,899 |
$71,962
1,116,723
kWh
|
$6,914
-
kW-mo/yr
|
$352 | $127 | ||
| TOTAL IMPLEMENTED | $64,285 | $11,821 |
$57,531
865,734
kWh
|
$6,275
-
kW-mo/yr
|
$352 | $127 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Primary Raw Material Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs