ITAC Assessment: UW0029
ITAC logo
ITAC Assessment: UW0029
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2009
Principal Product Plastic Containers
NAICS 326150: Urethane and Other Foam Product (except Polystyrene) Manufacturing
SIC 3086: Plastics Foam Products
Sales Range $50
M
to 100
M
# of Employees 70
Plant Area 40,000
ft2
Annual Production 500,000
pieces
Production Hrs. Annual 6,132
hrs
Location (State) Washington

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $217,007 6,657,880
kWh
Electricity Fees $552 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,661 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $34,661

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings
01 2.2622: Replace existing chiller with high efficiency model $13,416 $120,000 $8,018
272,615
kWh
$3,898
-
kW-mo/yr
$1,500
02 2.4113: Install motor voltage controller on lightly loaded motors $10,263 $17,000 $10,263
313,589
kWh
- -
03 2.2511: Insulate bare equipment $3,269 $3,800 $3,269
99,076
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $7,713 $9,934 $4,969
150,596
kWh
$1,665
-
kW-mo/yr
$1,079
TOTAL RECOMMENDED $34,661 $150,734 $26,519
835,876
kWh
$5,563
-
kW-mo/yr
$2,579
TOTAL IMPLEMENTED $34,661 $150,734 $26,519
835,876
kWh
$5,563
-
kW-mo/yr
$2,579
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs