| Assessment Year | 2005 |
|---|---|
| Principal Product | Transmission and Steering Components |
| NAICS | 336350: Motor Vehicle Transmission and Power Train Parts Manufacturing |
| SIC | 3714: Motor Vehicle Parts and Accessories |
| Sales Range | $10 M to 50M |
| # of Employees | 128 |
| Plant Area |
48,000
ft2
|
| Annual Production | 20,000,000
pieces
|
| Production Hrs. Annual | 5,304
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $112,787 | 3,077,259 |
kWh
|
$0.037 |
| Electricity Demand | $76,015 | 8,016 |
kW-mo/yr
|
$9.48 |
| Electricity Fees | $3,524 | - |
|
- |
| Natural Gas | $13,980 | 1,930 |
MMBtu
|
$7.24 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $56,239 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $45,052 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $32,977 | $1,275 |
$20,653
563,521
kWh
|
$12,324
-
kW-mo/yr
|
- | - | |
| 02 | 3.6193: Install equipment (eg compactor) to reduce disposal costs | $9,488 | $11,000 | - | - | - |
$9,488
-
gal
|
|
| 03 | 2.2437: Recover waste heat from equipment | $7,059 | $1,000 | - | - |
$7,059
-
MMBtu
|
- | |
| 04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,062 | $4,152 |
$1,972
53,801
kWh
|
$1,090
-
kW-mo/yr
|
- | - | |
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,954 | $2,000 |
$1,226
33,443
kWh
|
$728
-
kW-mo/yr
|
- | - | |
| 06 | 2.7124: Make a practice of turning off lights when not needed | $1,360 | - |
$1,360
37,102
kWh
|
- | - | - | |
| 07 | 2.4239: Eliminate or reduce compressed air usage | $339 | $1,000 |
$83
2,274
kWh
|
$256
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $56,239 | $20,427 |
$25,294
690,141
kWh
|
$14,398
-
kW-mo/yr
|
$7,059
-
MMBtu
|
$9,488
-
gal
|
||
| TOTAL IMPLEMENTED | $45,052 | $8,427 |
$23,851
650,765
kWh
|
$14,142
-
kW-mo/yr
|
$7,059
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs