| Assessment Year | 2005 |
|---|---|
| Principal Product | Fluid Conveyance Hose & Tube, Assemblies for the Aerospace Industry |
| NAICS | 332721: Precision Turned Product Manufacturing |
| SIC | 3451: Screw Machine Products |
| Sales Range | $50 M to 100M |
| # of Employees | 506 |
| Plant Area |
150,000
ft2
|
| Annual Production | 800,000
pieces
|
| Production Hrs. Annual | 6,000
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $362,325 | 6,354,965 |
kWh
|
$0.057 |
| Natural Gas | $165,857 | 24,231 |
MMBtu
|
$6.84 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $28,388 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Consumption Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7124: Make a practice of turning off lights when not needed | $12,587 | $640 |
$12,587
220,830
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $7,689 | $5,736 |
$7,689
134,886
kWh
|
- | - | |
| 03 | 2.2514: Cover open tanks | $2,342 | $3,510 | - |
$2,258
-
MMBtu
|
$84
-
Tgal
|
|
| 04 | 3.4151: Minimize water usage | $2,142 | $1,262 |
$(-2,524.0)
(-44,279)
kWh
|
- |
$4,666
-
Tgal
|
|
| 05 | 2.4221: Install compressor air intakes in coolest locations | $1,738 | $1,000 |
$1,738
30,485
kWh
|
- | - | |
| 06 | 2.2511: Insulate bare equipment | $1,070 | $1,938 | - |
$1,070
-
MMBtu
|
- | |
| 07 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $476 | $276 |
$476
8,344
kWh
|
- | - | |
| 08 | 2.7135: Install occupancy sensors | $344 | $225 |
$344
6,026
kWh
|
- | - | |
| TOTAL RECOMMENDED | $28,388 | $14,587 |
$20,310
356,292
kWh
|
$3,328
-
MMBtu
|
$4,750
-
Tgal
|
||
| TOTAL IMPLEMENTED | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Consumption Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs