ITAC Assessment: UF0258
ITAC logo
ITAC Assessment: UF0258
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Computer Imaging Systems
NAICS
n/a
SIC 3577: Computer Peripheral Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 165
Plant Area 60,000
ft2
Annual Production 25,000
pieces
Production Hrs. Annual 2,340
hrs
Location (State) Florida

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $80,354 1,766,413
kWh
Electricity Demand $38,121 4,076
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $39,461 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $39,047

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $4,278 - $2,309
51,290
kWh
$1,969
-
kW-mo/yr
-
02 2.7141: Lower light fixtures in high ceiling areas $833 - $403
9,086
kWh
$430
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $414 - $414
9,086
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,054 - $268
5,862
kWh
$76
-
kW-mo/yr
$710
05 2.3112: Store heated/ cooled water for use during peak demand periods $18,176 - - $18,176
-
kW-mo/yr
-
06 3.4155: Meter waste water $306 - - - $306
07 4.111: Add equipment/ operators to reduce production bottleneck $14,400 - - - $14,400
TOTAL RECOMMENDED $39,461 - $3,394
75,324
kWh
$20,651
-
kW-mo/yr
$15,416
TOTAL IMPLEMENTED $39,047 - $2,980
66,238
kWh
$20,651
-
kW-mo/yr
$15,416
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs