Assessment Year | 2004 |
---|---|
Principal Product | Ventilation Covers |
NAICS | 332323: Ornamental and Architectural Metal Work Manufacturing |
SIC | 3446: Architectural and Ornamental Metal Work |
Sales Range | $50 M to 100M |
# of Employees | 500 |
Plant Area |
813,264
ft2
|
Annual Production | 23,140,000
pieces
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $473,488 | 14,356,808 |
kWh
|
$0.033 |
Electricity Demand | $253,592 | 30,011 |
kW-mo/yr
|
$8.45 |
Electricity Fees | $15,065 | - |
|
- |
Natural Gas | $445,883 | 59,697 |
MMBtu
|
$7.47 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $139,178 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $42,675 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.2511: Insulate bare equipment | $41,018 | $37,327 | n/a | - | - |
$41,018
-
MMBtu
|
02 | 2.4224: Upgrade controls on compressors | $35,085 | $20,225 |
$25,638
925,827
kWh
|
$9,447
-
kW-mo/yr
|
- | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $26,517 | $31,338 | n/a |
$17,755
538,356
kWh
|
$8,762
-
kW-mo/yr
|
- |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $18,376 | $21,876 | n/a |
$8,996
272,788
kWh
|
$9,380
-
kW-mo/yr
|
- |
05 | 2.1233: Analyze flue gas for proper air/fuel ratio | $10,592 | $100 | - | - |
$10,592
-
MMBtu
|
|
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $7,590 | $100 |
$5,085
154,164
kWh
|
$2,505
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $139,178 | $110,966 |
$57,474
1,891,135
kWh
|
$30,094
-
kW-mo/yr
|
$51,610
-
MMBtu
|
||
TOTAL IMPLEMENTED | $42,675 | $20,325 |
$30,723
1,079,991
kWh
|
$11,952
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs