Assessment Year | 2003 |
---|---|
Principal Product | Blow Molded Plastics |
NAICS | 326199: All Other Plastics Product Manufacturing |
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 115 |
Plant Area |
56,000
ft2
|
Annual Production | 2,500,000
pieces
|
Production Hrs. Annual | 8,736
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $234,122 | 5,871,000 |
kWh
|
$0.040 |
Electricity Demand | $95,188 | 11,186 |
kW-mo/yr
|
$8.51 |
Electricity Fees | $6,396 | - |
|
- |
Natural Gas | $6,982 | 1,153 |
MMBtu
|
$6.06 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $37,855 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $9,740 | $6,270 |
$8,140
204,143
kWh
|
$1,600
-
kW-mo/yr
|
|
02 | 2.4221: Install compressor air intakes in coolest locations | $9,195 | $1,000 |
$7,115
178,367
kWh
|
$2,080
-
kW-mo/yr
|
|
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $8,670 | $300 |
$6,705
168,200
kWh
|
$1,965
-
kW-mo/yr
|
|
04 | 2.4131: Size electric motors for peak operating efficiency | $5,040 | $1,100 |
$3,900
97,775
kWh
|
$1,140
-
kW-mo/yr
|
|
05 | 2.2511: Insulate bare equipment | $4,180 | $645 |
$2,630
66,029
kWh
|
$1,550
-
kW-mo/yr
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,030 | $2,170 |
$800
19,970
kWh
|
$230
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $37,855 | $11,485 |
$29,290
734,484
kWh
|
$8,565
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs