| Assessment Year | 2002 |
|---|---|
| Principal Product | Ball Bearings |
| NAICS |
n/a
|
| SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
| Sales Range | $100 M to 500M |
| # of Employees | 369 |
| Plant Area |
173,300
ft2
|
| Annual Production | 22,000,000
pieces
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $532,106 | 18,391,200 |
kWh
|
$0.029 |
| Electricity Demand | $796,382 | 43,512 |
kW-mo/yr
|
$18.30 |
| Natural Gas | $331,086 | 67,549 |
MMBtu
|
$4.90 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $145,654 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $104,749 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.2437: Recover waste heat from equipment | $40,905 | $1,000 |
$40,905
2,445,964
kWh
|
- | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $35,927 | $71,714 |
$18,721
665,975
kWh
|
$17,206
-
kW-mo/yr
|
- | |
| 03 | 2.7221: Lower temperature during the winter season and vice-versa | $23,514 | $500 | - | - |
$23,514
-
MMBtu
|
|
| 04 | 2.4239: Eliminate or reduce compressed air usage | $22,460 | $3,600 |
$6,100
216,989
kWh
|
$16,360
-
kW-mo/yr
|
- | |
| 05 | 2.7132: Install timers on light switches in little used areas | $11,201 | $500 |
$11,201
397,488
kWh
|
- | - | |
| 06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $10,292 | $3,000 |
$5,363
190,787
kWh
|
$4,929
-
kW-mo/yr
|
- | |
| 07 | 2.7447: Install vinyl strip / high speed / air curtain doors | $1,355 | $1,468 |
$297
3,516
kWh
|
- |
$1,058
-
MMBtu
|
|
| TOTAL RECOMMENDED | $145,654 | $81,782 |
$82,587
3,920,719
kWh
|
$38,495
-
kW-mo/yr
|
$24,572
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $104,749 | $80,782 |
$41,682
1,474,755
kWh
|
$38,495
-
kW-mo/yr
|
$24,572
-
MMBtu
|
||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs