ITAC Assessment: UM0205
ITAC logo
ITAC Assessment: UM0205
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product forestry blades and saws
NAICS
n/a
SIC 3490:
Sales Range $10
M
to 50
M
# of Employees 69
Plant Area 92,000
ft2
Annual Production 3,120,000
lb
Production Hrs. Annual 6,000
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $202,645 5,696,535
kWh
Electricity Demand $145,988 1,280
kW-mo/yr
Electricity Fees $4,974 -
Natural Gas $23,231 4,768
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $41,135 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,594

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Ancillary Material Cost Savings
01 3.4111: Use closed cycle process to minimize waste water production $18,000 $5,940 - - $18,000
-
Tgal
-
02 2.3191: Use demand controller or load shedder $11,300 $15,000 - $11,300
-
kW-mo/yr
- -
03 2.5123: Reduce fluid flow rates $4,604 $1,600 $3,240
90,000
kWh
$1,364
-
kW-mo/yr
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,937 $11,015 $1,965
54,445
kWh
$972
-
kW-mo/yr
- -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $3,362 $300 $2,105
65,575
kWh
$1,257
-
kW-mo/yr
- -
06 2.4221: Install compressor air intakes in coolest locations $932 $1,000 $346
10,776
kWh
$209
-
kW-mo/yr
- $377
TOTAL RECOMMENDED $41,135 $34,855 $7,656
220,796
kWh
$15,102
-
kW-mo/yr
$18,000
-
Tgal
$377
TOTAL IMPLEMENTED $33,594 $22,240 $2,451
76,351
kWh
$12,766
-
kW-mo/yr
$18,000
-
Tgal
$377
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs