Assessment Year | 2002 |
---|---|
Principal Product | Non-metallic enclosures |
NAICS |
n/a
|
SIC | 3711: Motor Vehicles and Passenger Car Bodies |
Sales Range | $10 M to 50M |
# of Employees | 90 |
Plant Area |
96,920
ft2
|
Annual Production | 2,100,000
lb
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $106,848 | 3,007,358 |
kWh
|
$0.036 |
Electricity Demand | $59,040 | 6,276 |
kW-mo/yr
|
$9.41 |
Electricity Fees | $1,701 | - |
|
- |
Natural Gas | $24,666 | 5,199 |
MMBtu
|
$4.74 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,099 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $14,861 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,238 | $10,640 | n/a |
$2,163
59,772
kWh
|
$1,075
-
kW-mo/yr
|
- | - |
02 | 2.7111: Reduce illumination to minimum necessary levels | $100 | $1,150 |
$100
32,230
kWh
|
- | - | - | |
03 | 2.4221: Install compressor air intakes in coolest locations | $1,069 | $1,000 |
$711
19,924
kWh
|
$358
-
kW-mo/yr
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,487 | $450 |
$988
27,835
kWh
|
$499
-
kW-mo/yr
|
- | - | |
05 | 2.2511: Insulate bare equipment | $10,288 | $1,195 |
$10,288
183,711
kWh
|
- | - | - | |
06 | 2.2136: Install / repair insulation on steam lines | $737 | $1,145 | - | - | - |
$737
-
MMBtu
|
|
07 | 2.3212: Optimize plant power factor | $1,180 | $2,590 | - | - | $1,180 | - | |
TOTAL RECOMMENDED | $18,099 | $18,170 |
$14,250
323,472
kWh
|
$1,932
-
kW-mo/yr
|
$1,180 |
$737
-
MMBtu
|
||
TOTAL IMPLEMENTED | $14,861 | $7,530 |
$12,087
263,700
kWh
|
$857
-
kW-mo/yr
|
$1,180 |
$737
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs