Assessment Year | 2001 |
---|---|
Principal Product | Thermoformed Plastic Parts |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 97 |
Plant Area |
200,000
ft2
|
Annual Production | 10,500
ton
|
Production Hrs. Annual | 6,240
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $577,394 | 16,240,193 |
kWh
|
$0.036 |
Electricity Demand | $366,681 | 38,892 |
kW-mo/yr
|
$9.43 |
Electricity Fees | $5,539 | - |
|
- |
Natural Gas | $75,657 | 15,768 |
MMBtu
|
$4.80 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $70,433 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $66,089 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,119 | $4,832 |
$1,053
29,886
kWh
|
$1,066
-
kW-mo/yr
|
- | - | - | |
02 | 2.3212: Optimize plant power factor | $8,645 | $19,064 | - | - | $8,645 | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,004 | $450 |
$1,466
41,313
kWh
|
$538
-
kW-mo/yr
|
- | - | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $6,496 | $2,500 |
$5,015
133,901
kWh
|
$1,481
-
kW-mo/yr
|
- | - | - | |
05 | 2.7243: Improve air circulation with destratification fans / other methods | $4,344 | $1,750 | - | - | - |
$4,344
-
MMBtu
|
- | |
06 | 4.641: Eliminate shutdowns of controls due to overheating | $46,825 | $45,535 | - | - | - | - | $46,825 | |
TOTAL RECOMMENDED | $70,433 | $74,131 |
$7,534
205,100
kWh
|
$3,085
-
kW-mo/yr
|
$8,645 |
$4,344
-
MMBtu
|
$46,825 | ||
TOTAL IMPLEMENTED | $66,089 | $72,381 |
$7,534
205,100
kWh
|
$3,085
-
kW-mo/yr
|
$8,645 | - | $46,825 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs