ITAC Assessment: UM0190
ITAC logo
ITAC Assessment: UM0190
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Phamaceuticals
NAICS
n/a
SIC 2834: Pharmaceutical Preparations
Sales Range $100
M
to 500
M
# of Employees 480
Plant Area 450,000
ft2
Annual Production 0
units
Production Hrs. Annual 5,760
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,416,772 35,194,759
kWh
Electricity Demand $271,270 36,192
kW-mo/yr
Natural Gas $539,416 101,055
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $503,714 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $101,862

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $81,576 $80,632 $81,576
1,130,180
kWh
- - -
02 2.7135: Install occupancy sensors $20,468 $9,600 - $20,468
-
kW-mo/yr
- -
03 2.7221: Lower temperature during the winter season and vice-versa $82,700 $8,000 $78,424
1,090,000
kWh
- - $4,276
-
MMBtu
04 2.3113: Make ice during off peak hours for cooling $293,000 $360,000 - $293,000
-
kW-mo/yr
- -
05 2.3212: Optimize plant power factor $20,286 $8,250 - - $20,286 -
06 2.4221: Install compressor air intakes in coolest locations $5,684 $1,000 $5,684
72,869
kWh
- - -
TOTAL RECOMMENDED $503,714 $467,482 $165,684
2,293,049
kWh
$313,468
-
kW-mo/yr
$20,286 $4,276
-
MMBtu
TOTAL IMPLEMENTED $101,862 $88,882 $81,576
1,130,180
kWh
- $20,286 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs