Assessment Year | 2001 |
---|---|
Principal Product | Phamaceuticals |
NAICS |
n/a
|
SIC | 2834: Pharmaceutical Preparations |
Sales Range | $100 M to 500M |
# of Employees | 480 |
Plant Area |
450,000
ft2
|
Annual Production | 0
units
|
Production Hrs. Annual | 5,760
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $2,416,772 | 35,194,759 |
kWh
|
$0.069 |
Electricity Demand | $271,270 | 36,192 |
kW-mo/yr
|
$7.50 |
Natural Gas | $539,416 | 101,055 |
MMBtu
|
$5.34 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $503,714 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $101,862 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $81,576 | $80,632 |
$81,576
1,130,180
kWh
|
- | - | - | |
02 | 2.7135: Install occupancy sensors | $20,468 | $9,600 | - |
$20,468
-
kW-mo/yr
|
- | - | |
03 | 2.7221: Lower temperature during the winter season and vice-versa | $82,700 | $8,000 |
$78,424
1,090,000
kWh
|
- | - |
$4,276
-
MMBtu
|
|
04 | 2.3113: Make ice during off peak hours for cooling | $293,000 | $360,000 | - |
$293,000
-
kW-mo/yr
|
- | - | |
05 | 2.3212: Optimize plant power factor | $20,286 | $8,250 | - | - | $20,286 | - | |
06 | 2.4221: Install compressor air intakes in coolest locations | $5,684 | $1,000 |
$5,684
72,869
kWh
|
- | - | - | |
TOTAL RECOMMENDED | $503,714 | $467,482 |
$165,684
2,293,049
kWh
|
$313,468
-
kW-mo/yr
|
$20,286 |
$4,276
-
MMBtu
|
||
TOTAL IMPLEMENTED | $101,862 | $88,882 |
$81,576
1,130,180
kWh
|
- | $20,286 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs