Assessment Year | 1999 |
---|---|
Principal Product | Sport Beverages |
NAICS |
n/a
|
SIC | 2086: Bottled and Canned Soft Drinks and Carbonated Waters |
Sales Range | $50 M to 100M |
# of Employees | 180 |
Plant Area |
900,000
ft2
|
Annual Production | 8,000,000
pieces
|
Production Hrs. Annual | 6,888
hrs
|
Location (State) | Pennsylvania |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $308,415 | 5,995,018 |
kWh
|
$0.051 |
Electricity Demand | $74,789 | 12,004 |
kW-mo/yr
|
$6.23 |
Electricity Fees | $(-43,259.0) | - |
|
- |
Natural Gas | $338,252 | 111,021 |
MMBtu
|
$3.05 |
Fuel Oil #4 | $14,234 | 2,669 |
MMBtu
|
$5.33 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $187,326 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,153 | $13,162 |
$4,032
78,546
kWh
|
$1,121
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7135: Install occupancy sensors | $22,250 | $28,000 |
$22,250
432,298
kWh
|
- | - | - | - | - | |
03 | 2.7111: Reduce illumination to minimum necessary levels | $26,892 | $1,200 |
$22,199
432,591
kWh
|
$4,693
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $2,850 | $3,667 |
$2,850
223,623
kWh
|
- | - | - | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $3,190 | $1,500 |
$2,635
51,290
kWh
|
$555
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.2414: Use waste heat from hot flue gases to preheat | $50,969 | $43,100 | - | - |
$50,969
-
MMBtu
|
- | - | - | |
07 | 4.632: Change operating conditions | $15,421 | $500 | - | - | - | - | - | $15,421 | |
08 | 4.111: Add equipment/ operators to reduce production bottleneck | $1,740 | $180 | - | - | - | - | - | $1,740 | |
09 | 3.7211: Modify material application methods | $13,353 | - | - | - | - | - |
$13,353
-
gal
|
- | |
10 | 3.7214: Reduce or eliminate waste | $29,674 | $5,000 | - | - | - | - |
$29,674
-
gal
|
- | |
11 | 3.7223: Install shrouding on machines to prevent splashing | $15,834 | $6,000 | - | - | - |
$15,834
-
Tgal
|
- | - | |
TOTAL RECOMMENDED | $187,326 | $102,309 |
$53,966
1,218,348
kWh
|
$6,369
-
kW-mo/yr
|
$50,969
-
MMBtu
|
$15,834
-
Tgal
|
$43,027
-
gal
|
$17,161 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs