ITAC Assessment: TA0102
ITAC logo
ITAC Assessment: TA0102
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Scrap Processing Equipment
NAICS 332710: Machine Shops
SIC 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 59
Plant Area 35,000
ft2
Annual Production 55
lb
Production Hrs. Annual 2,134
hrs
Location (State) Texas

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $68,115 839,040
kWh
Electricity Demand $40,362 5,428
kW-mo/yr
Natural Gas $14,719 1,836
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $27,587 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $26,172

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.3137: Use power during off-peak periods $20,445 - - $20,445
-
kW-mo/yr
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,027 $110 $514
7,801
kWh
$513
-
kW-mo/yr
03 2.7121: Utilize daylight whenever possible in lieu of artificial light $4,700 $1,800 $4,700
71,284
kWh
-
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,170 - $590
8,909
kWh
$580
-
kW-mo/yr
05 2.7142: Utilize higher efficiency lamps and/or ballasts $245 $148 $195
2,943
kWh
$50
-
kW-mo/yr
TOTAL RECOMMENDED $27,587 $2,058 $5,999
90,937
kWh
$21,588
-
kW-mo/yr
TOTAL IMPLEMENTED $26,172 $1,910 $5,214
79,085
kWh
$20,958
-
kW-mo/yr
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs