| Assessment Year | 1998 |
|---|---|
| Principal Product | Heat Vent Air Equipment and Fixtures |
| NAICS |
n/a
|
| SIC | 3444: Sheet Metal Work |
| Sales Range | $10 M to 50M |
| # of Employees | 90 |
| Plant Area |
133,990
ft2
|
| Annual Production | 175
pieces
|
| Production Hrs. Annual | 4,680
hrs
|
| Location (State) | Missouri |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $35,948 | 840,270 |
kWh
|
$0.043 |
| Electricity Demand | $17,408 | 373 |
kW-mo/yr
|
$46.67 |
| Electricity Fees | $3,588 | - |
|
- |
| Natural Gas | $53,575 | 8,451 |
MMBtu
|
$6.34 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $73,970 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,151 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 4.711: Initiate a total quality management program | $23,659 | $30,000 | - | - | - | $23,659 | |
| 02 | 4.432: Cross-train personnel to avoid lost time | $14,206 | $25,000 | - | - | - | $14,206 | |
| 03 | 4.611: Begin a practice of predictive / preventative maintenance | $10,720 | $3,700 | - | - | - | $10,720 | |
| 04 | 4.514: Re-arrange equipment layout to reduce handling costs | $6,499 | $12,500 | - | - | - | $6,499 | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $744 | $1,472 |
$562
12,016
kWh
|
$182
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $280 | $491 |
$210
4,396
kWh
|
$70
-
kW-mo/yr
|
- | - | |
| 07 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $280 | $552 |
$252
5,275
kWh
|
$28
-
kW-mo/yr
|
- | - | |
| 08 | 2.4231: Reduce the pressure of compressed air to the minimum required | $641 | $80 |
$552
11,723
kWh
|
$89
-
kW-mo/yr
|
- | - | |
| 09 | 2.4221: Install compressor air intakes in coolest locations | $390 | $100 |
$259
5,569
kWh
|
$131
-
kW-mo/yr
|
- | - | |
| 10 | 2.4133: Use most efficient type of electric motors | $1,452 | $2,554 |
$1,162
24,619
kWh
|
$290
-
kW-mo/yr
|
- | - | |
| 11 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $79 | - |
$65
1,465
kWh
|
$14
-
kW-mo/yr
|
- | - | |
| 12 | 3.1191: Change procedures / equipment / operating conditions | $8,305 | $20,000 | - | - |
$8,305
-
lb
|
- | |
| 13 | 2.7496: Install partitions to reduce size of conditioned space | $6,715 | $17,500 | - | - |
$6,715
-
lb
|
- | |
| TOTAL RECOMMENDED | $73,970 | $113,949 |
$3,062
65,063
kWh
|
$804
-
kW-mo/yr
|
$15,020
-
lb
|
$55,084 | ||
| TOTAL IMPLEMENTED | $17,151 | $29,617 |
$2,258
48,065
kWh
|
$687
-
kW-mo/yr
|
- | $14,206 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs