| Assessment Year | 2001 |
|---|---|
| Principal Product | Aluminum Castings |
| NAICS |
n/a
|
| SIC | 3363: Aluminum Die-Castings |
| Sales Range | $10 M to 50M |
| # of Employees | 191 |
| Plant Area |
136,250
ft2
|
| Annual Production | 12,000,000
lb
|
| Production Hrs. Annual | 8,736
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $442,599 | 11,870,164 |
kWh
|
$0.037 |
| Electricity Demand | $187,447 | 9,636 |
kW-mo/yr
|
$19.45 |
| Electricity Fees | $14,270 | - |
|
- |
| Natural Gas | $590,226 | 129,313 |
MMBtu
|
$4.56 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $101,829 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $58,468 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $568 | $375 |
$568
10,516
kWh
|
- | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $361 | $1,000 |
$361
6,680
kWh
|
- | |
| 03 | 2.2531: Re-size charging openings or add movable cover or door | $57,900 | $28,900 | - |
$57,900
-
MMBtu
|
|
| 04 | 2.2437: Recover waste heat from equipment | $43,000 | $100,000 | - |
$43,000
-
MMBtu
|
|
| TOTAL RECOMMENDED | $101,829 | $130,275 |
$929
17,196
kWh
|
$100,900
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $58,468 | $29,275 |
$568
10,516
kWh
|
$57,900
-
MMBtu
|
||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs