Assessment Year | 2001 |
---|---|
Principal Product | Aluminum Castings |
NAICS |
n/a
|
SIC | 3365: Aluminum Foundries |
Sales Range | $5 M to 10M |
# of Employees | 46 |
Plant Area |
55,000
ft2
|
Annual Production | 480
ton
|
Production Hrs. Annual | 2,040
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $69,535 | 1,292,497 |
kWh
|
$0.054 |
Electricity Demand | $36,501 | 3,864 |
kW-mo/yr
|
$9.45 |
Electricity Fees | $(-824.0) | - |
|
- |
Natural Gas | $132,092 | 28,959 |
MMBtu
|
$4.56 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $20,087 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,150 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,864 | $450 |
$1,301
29,601
kWh
|
$1,563
-
kW-mo/yr
|
- | |
02 | 2.4221: Install compressor air intakes in coolest locations | $994 | $1,250 |
$635
21,395
kWh
|
$359
-
kW-mo/yr
|
- | |
03 | 2.2515: Use optimum thickness insulation | $4,406 | $2,264 | - | - |
$4,406
-
MMBtu
|
|
04 | 2.2414: Use waste heat from hot flue gases to preheat | $3,048 | $6,185 | - | - |
$3,048
-
MMBtu
|
|
05 | 2.7243: Improve air circulation with destratification fans / other methods | $7,489 | $1,400 | - | - |
$7,489
-
MMBtu
|
|
06 | 2.2437: Recover waste heat from equipment | $1,286 | $500 | - | - |
$1,286
-
MMBtu
|
|
TOTAL RECOMMENDED | $20,087 | $12,049 |
$1,936
50,996
kWh
|
$1,922
-
kW-mo/yr
|
$16,229
-
MMBtu
|
||
TOTAL IMPLEMENTED | $4,150 | $950 |
$1,301
29,601
kWh
|
$1,563
-
kW-mo/yr
|
$1,286
-
MMBtu
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs