Assessment Year | 2000 |
---|---|
Principal Product | Grey Iron Castings |
NAICS |
n/a
|
SIC | 3321: Gray and Ductile Iron Foundries |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
60,000
ft2
|
Annual Production | 2,000
ton
|
Production Hrs. Annual | 2,805
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $128,445 | 2,033,998 |
kWh
|
$0.063 |
Electricity Demand | $33,209 | 20,412 |
kW-mo/yr
|
$1.63 |
Electricity Fees | $(-346.0) | - |
|
- |
Natural Gas | $17,303 | 4,582 |
MMBtu
|
$3.78 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $8,658 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $573 | $800 |
$311
9,086
kWh
|
$262
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,521 | $225 |
$803
22,274
kWh
|
$718
-
kW-mo/yr
|
- | |
03 | 2.4131: Size electric motors for peak operating efficiency | $758 | $700 |
$309
8,499
kWh
|
$449
-
kW-mo/yr
|
- | |
04 | 2.4224: Upgrade controls on compressors | $3,506 | $800 |
$2,489
139,508
kWh
|
$1,017
-
kW-mo/yr
|
- | |
05 | 2.2437: Recover waste heat from equipment | $2,300 | $750 | - | - |
$2,300
-
MMBtu
|
|
TOTAL RECOMMENDED | $8,658 | $3,275 |
$3,912
179,367
kWh
|
$2,446
-
kW-mo/yr
|
$2,300
-
MMBtu
|
||
TOTAL IMPLEMENTED | - | - | - | - | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs