ITAC Assessment: UM0153
ITAC logo
ITAC Assessment: UM0153
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Glass Products
NAICS
n/a
SIC 3200:
Sales Range $10
M
to 50
M
# of Employees 130
Plant Area 42,000
ft2
Annual Production 12,000
thousand feet
Production Hrs. Annual 7,344
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $172,037 5,364,889
kWh
Electricity Demand $158,471 17,592
kW-mo/yr
Electricity Fees $23,307 -
Natural Gas $1,814 403
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $51,700 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,500

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Primary Raw Material Savings
01 2.2628: Utilize a less expensive cooling method $4,796 $2,000 $4,796
69,461
kWh
- - -
02 2.4221: Install compressor air intakes in coolest locations $1,023 $800 $681
21,102
kWh
$342
-
kW-mo/yr
- -
03 3.5211: Reuse scrap glass as feed stock $7,831 - - - $7,831
-
lb
-
04 3.5311: Recover and reuse waste material $17,500 $1,000 - - $17,500
-
lb
-
05 4.421: Modify current incentive program $20,550 $32,800 - - - $20,550
TOTAL RECOMMENDED $51,700 $36,600 $5,477
90,563
kWh
$342
-
kW-mo/yr
$25,331
-
lb
$20,550
TOTAL IMPLEMENTED $17,500 $1,000 - - $17,500
-
lb
-
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs