| Assessment Year | 2000 |
|---|---|
| Principal Product | Glass Products |
| NAICS |
n/a
|
| SIC | 3200: |
| Sales Range | $10 M to 50M |
| # of Employees | 130 |
| Plant Area |
42,000
ft2
|
| Annual Production | 12,000
thousand feet
|
| Production Hrs. Annual | 7,344
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $172,037 | 5,364,889 |
kWh
|
$0.032 |
| Electricity Demand | $158,471 | 17,592 |
kW-mo/yr
|
$9.01 |
| Electricity Fees | $23,307 | - |
|
- |
| Natural Gas | $1,814 | 403 |
MMBtu
|
$4.50 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $51,700 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $17,500 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Primary Raw Material Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.2628: Utilize a less expensive cooling method | $4,796 | $2,000 |
$4,796
69,461
kWh
|
- | - | - | |
| 02 | 2.4221: Install compressor air intakes in coolest locations | $1,023 | $800 |
$681
21,102
kWh
|
$342
-
kW-mo/yr
|
- | - | |
| 03 | 3.5211: Reuse scrap glass as feed stock | $7,831 | - | - | - |
$7,831
-
lb
|
- | |
| 04 | 3.5311: Recover and reuse waste material | $17,500 | $1,000 | - | - |
$17,500
-
lb
|
- | |
| 05 | 4.421: Modify current incentive program | $20,550 | $32,800 | - | - | - | $20,550 | |
| TOTAL RECOMMENDED | $51,700 | $36,600 |
$5,477
90,563
kWh
|
$342
-
kW-mo/yr
|
$25,331
-
lb
|
$20,550 | ||
| TOTAL IMPLEMENTED | $17,500 | $1,000 | - | - |
$17,500
-
lb
|
- | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs