Assessment Year | 1999 |
---|---|
Principal Product | Metal Fittings |
NAICS |
n/a
|
SIC | 3451: Screw Machine Products |
Sales Range | $5 M to 10M |
# of Employees | 91 |
Plant Area |
51,000
ft2
|
Annual Production | 6,110,846
pieces
|
Production Hrs. Annual | 4,386
hrs
|
Location (State) | Ohio |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,423 | 1,293,669 |
kWh
|
$0.042 |
Electricity Demand | $16,033 | 4,476 |
kW-mo/yr
|
$3.58 |
Electricity Fees | $580 | - |
|
- |
Natural Gas | $5,723 | 1,050 |
MMBtu
|
$5.45 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $377,187 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $9,954 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4221: Install compressor air intakes in coolest locations | $836 | $500 |
$678
16,120
kWh
|
$158
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $618 | $200 |
$500
12,016
kWh
|
$118
-
kW-mo/yr
|
- | - | - | - | - | - | |
03 | 2.2437: Recover waste heat from equipment | $2,322 | $1,500 | - | - | - |
$2,322
-
MMBtu
|
- | - | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $4,107 | $10,500 |
$4,627
110,199
kWh
|
$1,933
-
kW-mo/yr
|
- |
$(-2,453.0)
-
MMBtu
|
- | - | - | - | |
05 | 2.8114: Change rate schedules or other changes in utility service | $3,804 | - | - | - | $3,804 | - | - | - | - | - | |
06 | 3.4112: Recovery metals from rinse water(evap., ion exchange, ro, electrolysis, electrodialysis) and reuse rinse water | $8,500 | $40,000 | - | - | - | - |
$3,850
-
gal
|
$(-490.0) | $5,140 | - | |
07 | 4.511: Expand operations into unused space | $357,000 | $714,000 | - | - | - | - | - | - | - | $357,000 | |
TOTAL RECOMMENDED | $377,187 | $766,700 |
$5,805
138,335
kWh
|
$2,209
-
kW-mo/yr
|
$3,804 |
$(-131.0)
-
MMBtu
|
$3,850
-
gal
|
$(-490.0) | $5,140 | $357,000 | ||
TOTAL IMPLEMENTED | $9,954 | $40,700 |
$1,178
28,136
kWh
|
$276
-
kW-mo/yr
|
- | - |
$3,850
-
gal
|
$(-490.0) | $5,140 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs