Assessment Year | 1999 |
---|---|
Principal Product | Abrasive Tumbling Media |
NAICS |
n/a
|
SIC | 3291: Abrasive Products |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
70,000
ft2
|
Annual Production | 6,000,000
lb
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $62,374 | 900,059 |
kWh
|
$0.069 |
Electricity Demand | $18,744 | 1,488 |
kW-mo/yr
|
$12.60 |
Electricity Fees | $(-766.0) | - |
|
- |
Natural Gas | $159,684 | 45,118 |
MMBtu
|
$3.54 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $48,049 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $40,364 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $1,661 | $110 |
$1,661
16,706
kWh
|
- | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $647 | $1,000 |
$497
7,913
kWh
|
$150
-
kW-mo/yr
|
- | - | - | |
03 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $1,285 | $350 |
$988
15,826
kWh
|
$297
-
kW-mo/yr
|
- | - | - | |
04 | 2.1122: Re-size charging openings or add a movable door on equipment | $5,837 | $9,350 | - | - |
$5,837
-
MMBtu
|
- | - | |
05 | 2.2515: Use optimum thickness insulation | $1,848 | $2,100 | - | - |
$1,848
-
MMBtu
|
- | - | |
06 | 3.1192: Reduce scrap production | $29,091 | $5,000 | - | - | - |
$29,091
-
lb
|
- | |
07 | 4.444: Install system to collect scrap | $7,680 | $584 | - | - | - | - | $7,680 | |
TOTAL RECOMMENDED | $48,049 | $18,494 |
$3,146
40,445
kWh
|
$447
-
kW-mo/yr
|
$7,685
-
MMBtu
|
$29,091
-
lb
|
$7,680 | ||
TOTAL IMPLEMENTED | $40,364 | $7,044 |
$3,146
40,445
kWh
|
$447
-
kW-mo/yr
|
- |
$29,091
-
lb
|
$7,680 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs