ITAC Assessment: UM0144
ITAC logo
ITAC Assessment: UM0144
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Abrasive Tumbling Media
NAICS
n/a
SIC 3291: Abrasive Products
Sales Range $1
M
to 5
M
# of Employees 25
Plant Area 70,000
ft2
Annual Production 6,000,000
lb
Production Hrs. Annual 8,568
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $62,374 900,059
kWh
Electricity Demand $18,744 1,488
kW-mo/yr
Electricity Fees $(-766.0) -
Natural Gas $159,684 45,118
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $48,049 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $40,364

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Product Savings
01 2.7111: Reduce illumination to minimum necessary levels $1,661 $110 $1,661
16,706
kWh
- - - -
02 2.4221: Install compressor air intakes in coolest locations $647 $1,000 $497
7,913
kWh
$150
-
kW-mo/yr
- - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,285 $350 $988
15,826
kWh
$297
-
kW-mo/yr
- - -
04 2.1122: Re-size charging openings or add a movable door on equipment $5,837 $9,350 - - $5,837
-
MMBtu
- -
05 2.2515: Use optimum thickness insulation $1,848 $2,100 - - $1,848
-
MMBtu
- -
06 3.1192: Reduce scrap production $29,091 $5,000 - - - $29,091
-
lb
-
07 4.444: Install system to collect scrap $7,680 $584 - - - - $7,680
TOTAL RECOMMENDED $48,049 $18,494 $3,146
40,445
kWh
$447
-
kW-mo/yr
$7,685
-
MMBtu
$29,091
-
lb
$7,680
TOTAL IMPLEMENTED $40,364 $7,044 $3,146
40,445
kWh
$447
-
kW-mo/yr
- $29,091
-
lb
$7,680
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs