Assessment Year | 2024 |
---|---|
Principal Product | Medical equipment |
NAICS | 339999: All Other Miscellaneous Manufacturing |
SIC | 3999: Manufacturing Industries, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 221 |
Plant Area |
29,000
ft2
|
Annual Production | 3,000,000
pieces
|
Production Hrs. Annual | 5,840
hrs
|
Location (State) | Utah |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $54,556 | 720,640 |
kWh
|
$0.076 |
Natural Gas | $31,307 | 2,629 |
MMBtu
|
$11.91 |
TOTAL YEARLY COSTS | $85,863 | |||
RECOMMENDED SAVINGS* | $35,469 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $33,429 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $10,990 | $184,280 |
$10,990
144,580
kWh
|
- | - | |
02 | 2.7314: Reduce ventilation air | $7,109 | $28,950 |
$2,556
33,636
kWh
|
$4,552
-
MMBtu
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,340 | $23,500 |
$5,340
70,320
kWh
|
- | - | |
04 | 2.6218: Turn off equipment when not in use | $6,350 | $8,970 |
$6,350
83,554
kWh
|
- | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $3,430 | $3,000 |
$3,430
45,150
kWh
|
- | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $2,040 | $375 |
$2,040
26,880
kWh
|
- | - | |
07 | 2.8123: Pay utility bills on time | $210 | $150 | - | - | $210 | |
TOTAL RECOMMENDED | $35,469 | $249,225 |
$30,706
404,120
kWh
|
$4,552
-
MMBtu
|
$210 | ||
TOTAL IMPLEMENTED | $33,429 | $248,850 |
$28,666
377,240
kWh
|
$4,552
-
MMBtu
|
$210 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs