| Assessment Year | 1999 |
|---|---|
| Principal Product | Plastic Orthopedic Implants and Injection Molded Parts |
| NAICS |
n/a
|
| SIC | 2821: Plastics Materials, Synthetic Resins, and Nonvulcanizable Elastomers |
| Sales Range | $1 M to 5M |
| # of Employees | 56 |
| Plant Area |
18,000
ft2
|
| Annual Production | 7,500
lb
|
| Production Hrs. Annual | 2,168
hrs
|
| Location (State) | Michigan |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $60,814 | 611,372 |
kWh
|
$0.099 |
| Electricity Fees | $(-1,410.0) | - |
|
- |
| Natural Gas | $1,022 | 160 |
MMBtu
|
$6.39 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $204,502 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $6,107 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Solid Waste (non-haz) Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.7135: Install occupancy sensors | $336 | $300 |
$336
3,517
kWh
|
- | - | |
| 02 | 2.6218: Turn off equipment when not in use | $461 | - |
$461
4,689
kWh
|
- | - | |
| 03 | 2.4221: Install compressor air intakes in coolest locations | $198 | $500 |
$198
2,052
kWh
|
- | - | |
| 04 | 3.5212: Regrind, reuse, or sell scrap plastic parts | $1,836 | $200 | - |
$1,836
-
lb
|
- | |
| 05 | 3.5316: Contract a wood pallet recycling company | $762 | $200 | - |
$762
-
lb
|
- | |
| 06 | 4.425: Eliminate/reduce redundant inspections | $5,909 | $3,434 | - | - | $5,909 | |
| 07 | 4.111: Add equipment/ operators to reduce production bottleneck | $195,000 | $10,000 | - | - | $195,000 | |
| TOTAL RECOMMENDED | $204,502 | $14,634 |
$995
10,258
kWh
|
$2,598
-
lb
|
$200,909 | ||
| TOTAL IMPLEMENTED | $6,107 | $3,934 |
$198
2,052
kWh
|
- | $5,909 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Solid Waste (non-haz) Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs