Assessment Year | 2015 |
---|---|
Principal Product | Metal Heat Treating |
NAICS | 332811: Metal Heat Treating |
SIC | 3399: Primary Metal Products, Not Elsewhere Classified |
Sales Range | $1 M to 5M |
# of Employees | 16 |
Plant Area |
17,000
ft2
|
Annual Production | 173,680
lb
|
Production Hrs. Annual | 4,160
hrs
|
Location (State) | Washington |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $265,220 | 3,700,829 |
kWh
|
$0.072 |
Electricity Demand | $84,528 | 13,488 |
kW-mo/yr
|
$6.27 |
Natural Gas | $59,647 | 7,992 |
MMBtu
|
$7.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $4,321 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,692 | $15 |
$1,450
20,133
kWh
|
$242
-
kW-mo/yr
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $879 | $910 |
$753
10,460
kWh
|
$126
-
kW-mo/yr
|
|
03 | 2.2511: Insulate bare equipment | $826 | $968 |
$826
11,474
kWh
|
- | |
04 | 2.2514: Cover open tanks | $44 | $50 |
$10
136
kWh
|
$34
-
kW-mo/yr
|
|
05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $660 | $3,120 |
$531
7,379
kWh
|
$129
-
kW-mo/yr
|
|
06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $220 | $600 |
$220
3,060
kWh
|
- | |
TOTAL RECOMMENDED | $4,321 | $5,663 |
$3,790
52,642
kWh
|
$531
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs