ITAC Assessment: UM0138
ITAC logo
ITAC Assessment: UM0138
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Wood Pallets
NAICS
n/a
SIC 2448: Wood Pallets and Skids
Sales Range $1
M
to 5
M
# of Employees 23
Plant Area 21,500
ft2
Annual Production 400,000
pieces
Production Hrs. Annual 2,470
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $38,124 437,866
kWh
Electricity Fees $5 -
Natural Gas $6,009 1,576
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,165 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,824

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Natural Gas Savings Solid Waste (non-haz) Savings By-product Production Savings
01 2.6218: Turn off equipment when not in use $1,289 - $1,289
14,947
kWh
- - -
02 2.4221: Install compressor air intakes in coolest locations $408 $300 $408
4,689
kWh
- - -
03 2.2437: Recover waste heat from equipment $2,541 $2,100 - $2,541
-
MMBtu
- -
04 3.5311: Recover and reuse waste material $10,800 $50,000 - - $10,800
-
lb
-
05 4.445: Install equipment to move product $5,127 - - - - $5,127
TOTAL RECOMMENDED $20,165 $52,400 $1,697
19,636
kWh
$2,541
-
MMBtu
$10,800
-
lb
$5,127
TOTAL IMPLEMENTED $6,824 $300 $1,697
19,636
kWh
- - $5,127
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs