Assessment Year | 1999 |
---|---|
Principal Product | Metal Furniture |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $100 M to 500M |
# of Employees | 490 |
Plant Area |
435,600
ft2
|
Annual Production | 243,692
pieces
|
Production Hrs. Annual | 5,250
hrs
|
Location (State) | Idaho |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $509,857 | 12,090,563 |
kWh
|
$0.042 |
Electricity Demand | $55,233 | 282,852 |
kW-mo/yr
|
$0.20 |
Electricity Fees | $1,362 | - |
|
- |
Natural Gas | $271,499 | 86,557 |
MMBtu
|
$3.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $2,971,487 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $2,959,732 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Ancillary Material Cost Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $11,755 | $9,290 |
$9,111
242,966
kWh
|
$2,644
-
kW-mo/yr
|
- | - | - | |
02 | 2.4224: Upgrade controls on compressors | $21,932 | $6,000 |
$19,678
524,912
kWh
|
$2,254
-
kW-mo/yr
|
- | - | - | |
03 | 4.111: Add equipment/ operators to reduce production bottleneck | $2,610,000 | $93,000 | - | - | - | - | $2,610,000 | |
04 | 4.321: Optimize production lot sizes and inventories | $327,800 | $87,400 | - | - | $(-4,700.0) | $332,500 | - | |
TOTAL RECOMMENDED | $2,971,487 | $195,690 |
$28,789
767,878
kWh
|
$4,898
-
kW-mo/yr
|
$(-4,700.0) | $332,500 | $2,610,000 | ||
TOTAL IMPLEMENTED | $2,959,732 | $186,400 |
$19,678
524,912
kWh
|
$2,254
-
kW-mo/yr
|
$(-4,700.0) | $332,500 | $2,610,000 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs