ITAC Assessment: UM0134
ITAC logo
ITAC Assessment: UM0134
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Wrought Iron Furniture
NAICS
n/a
SIC 2514: Metal Household Furniture
Sales Range $10
M
to 50
M
# of Employees 262
Plant Area 44,000
ft2
Annual Production 3,744
ton
Production Hrs. Annual 6,084
hrs
Location (State) Michigan

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $166,519 4,925,264
kWh
Electricity Demand $108,372 12,744
kW-mo/yr
Electricity Fees $42,086 -
Natural Gas $159,208 45,267
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $987,653 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Solid Waste (non-haz) Savings Personnel Changes Savings
01 2.4221: Install compressor air intakes in coolest locations $1,206 $1,000 $817
25,791
kWh
$389
-
kW-mo/yr
- - -
02 2.1121: Use insulation in furnaces to facilitate heating / cooling $11,967 $2,000 $5,263
166,178
kWh
$6,704
-
kW-mo/yr
- - -
03 2.7243: Improve air circulation with destratification fans / other methods $27,764 $36,550 - - $27,764
-
MMBtu
- -
04 3.5212: Regrind, reuse, or sell scrap plastic parts $1,800 - - - - $1,800
-
lb
-
05 4.111: Add equipment/ operators to reduce production bottleneck $944,916 $200,000 - - - - $944,916
TOTAL RECOMMENDED $987,653 $239,550 $6,080
191,969
kWh
$7,093
-
kW-mo/yr
$27,764
-
MMBtu
$1,800
-
lb
$944,916
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs