Assessment Year | 1998 |
---|---|
Principal Product | superabrasive electroplated tooling |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $1 M to 5M |
# of Employees | 25 |
Plant Area |
10,400
ft2
|
Annual Production | 100,000
pieces
|
Production Hrs. Annual | 6,864
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $31,569 | 312,720 |
kWh
|
$0.10 |
Electricity Fees | $982 | - |
|
- |
Natural Gas | $3,169 | 728 |
MMBtu
|
$4.35 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $37,339 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $25,322 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,850 | $2,048 |
$1,850
18,464
kWh
|
- | - | - | - | |
02 | 2.4221: Install compressor air intakes in coolest locations | $511 | $1,000 |
$511
5,275
kWh
|
- | - | - | - | |
03 | 2.2437: Recover waste heat from equipment | $761 | $990 |
$761
51,290
kWh
|
- | - | - | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $12,085 | $6,000 |
$14,712
141,559
kWh
|
$(-2,627.0)
-
MMBtu
|
- | - | - | |
05 | 3.3131: Use evaporation to concentrate material | $8,359 | $12,000 | - | - |
$8,359
-
Tgal
|
- | - | |
06 | 3.3122: Use filtration, centrifuging to remove contaminants | $12,017 | $11,000 | - | - | - |
$12,017
-
gal
|
- | |
07 | 4.125: | $1,756 | $3,350 | - | - | - | - | $1,756 | |
TOTAL RECOMMENDED | $37,339 | $36,388 |
$17,834
216,588
kWh
|
$(-2,627.0)
-
MMBtu
|
$8,359
-
Tgal
|
$12,017
-
gal
|
$1,756 | ||
TOTAL IMPLEMENTED | $25,322 | $25,388 |
$17,834
216,588
kWh
|
$(-2,627.0)
-
MMBtu
|
$8,359
-
Tgal
|
- | $1,756 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs