Assessment Year | 1998 |
---|---|
Principal Product | Metal Stampings |
NAICS |
n/a
|
SIC | 3469: Metal Stampings, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 100 |
Plant Area |
42,000
ft2
|
Annual Production | 5,000,000
pieces
|
Production Hrs. Annual | 4,335
hrs
|
Location (State) | Michigan |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $98,744 | 992,673 |
kWh
|
$0.099 |
Electricity Fees | $(-3,290.0) | - |
|
- |
Natural Gas | $163 | 35 |
MMBtu
|
$4.66 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $14,069 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $3,137 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings |
---|---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $852 | $1,450 |
$449
9,086
kWh
|
$403
-
kW-mo/yr
|
- | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,169 | $2,110 |
$580
9,965
kWh
|
$589
-
kW-mo/yr
|
- | |
03 | 2.7135: Install occupancy sensors | $407 | $400 |
$407
7,034
kWh
|
- | - | |
04 | 2.4221: Install compressor air intakes in coolest locations | $1,116 | $1,000 |
$1,116
19,343
kWh
|
- | - | |
05 | 2.8114: Change rate schedules or other changes in utility service | $10,525 | $40,250 | - | - | $10,525 | |
TOTAL RECOMMENDED | $14,069 | $45,210 |
$2,552
45,428
kWh
|
$992
-
kW-mo/yr
|
$10,525 | ||
TOTAL IMPLEMENTED | $3,137 | $4,560 |
$2,145
38,394
kWh
|
$992
-
kW-mo/yr
|
- |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs