ITAC Assessment: UM0107
ITAC logo
ITAC Assessment: UM0107
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Water deflectors for automotive industry
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 171,000
ft2
Annual Production 7,900,000
pieces
Production Hrs. Annual 6,240
hrs
Location (State) Ohio

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $44,112 543,083
kWh
Electricity Demand $6,770 600
kW-mo/yr
Electricity Fees $9,988 -
Natural Gas $10,570 2,079
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $34,255 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Fees Savings Solid Waste (non-haz) Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,746 $3,572 $1,746
23,447
kWh
- - -
02 2.4221: Install compressor air intakes in coolest locations $250 $250 $250
5,275
kWh
- - -
03 2.8114: Change rate schedules or other changes in utility service $7,179 $250 - $7,179 - -
04 3.5316: Contract a wood pallet recycling company $130 $100 - - $130
-
lb
-
05 4.423: Move product using mechanical means $10,400 $2,250 - - - $10,400
06 4.122: Develop standard procedures to improve internal yields $14,550 $5,200 - - - $14,550
TOTAL RECOMMENDED $34,255 $11,622 $1,996
28,722
kWh
$7,179 $130
-
lb
$24,950
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Fees Savings Solid Waste (non-haz) Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs