Assessment Year | 2000 |
---|---|
Principal Product | Paperboard cartons |
NAICS |
n/a
|
SIC | 2671: Packaging Paper and Plastics Film, Coated and Laminated |
Sales Range | $10 M to 50M |
# of Employees | 150 |
Plant Area |
180,000
ft2
|
Annual Production | 223,500,000
pieces
|
Production Hrs. Annual | 6,000
hrs
|
Location (State) | North Carolina |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $211,407 | 8,149,473 |
kWh
|
$0.026 |
Electricity Demand | $153,302 | 16,227 |
kW-mo/yr
|
$9.45 |
Electricity Fees | $13,789 | - |
|
- |
Natural Gas | $33,497 | 5,131 |
MMBtu
|
$6.53 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $127,259 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,432 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,843 | $10,160 |
$1,004
39,859
kWh
|
$839
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $12,718 | $50,100 |
$3,961
157,386
kWh
|
$2,962
-
kW-mo/yr
|
- | $5,795 | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,432 | $3,250 |
$2,374
94,373
kWh
|
$2,058
-
kW-mo/yr
|
- | - | |
04 | 2.1311: Replace electrically-operated equipment with fossil fuel equipment | $87,421 | $288,000 |
$78,003
3,096,424
kWh
|
$50,560
-
kW-mo/yr
|
$(-43,142.0)
-
MMBtu
|
$2,000 | |
05 | 2.2491: Use cooling air which cools hot work pieces for space heating | $20,845 | $10,000 |
$13,645
541,618
kWh
|
$7,200
-
kW-mo/yr
|
- | - | |
TOTAL RECOMMENDED | $127,259 | $361,510 |
$98,987
3,929,660
kWh
|
$63,619
-
kW-mo/yr
|
$(-43,142.0)
-
MMBtu
|
$7,795 | ||
TOTAL IMPLEMENTED | $4,432 | $3,250 |
$2,374
94,373
kWh
|
$2,058
-
kW-mo/yr
|
- | - |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs